April Update: The Shoring Continues

Things keep moving right along at our site these days! We’re now two months into the shoring process, which should take about 6 months. Our construction workers have been working tirelessly to drill and dig into the perimeter of our site for the shoring, which will act as a support system during construction. Here’s a …

DSC_0555

Let The Digging Begin!

Things couldn’t be better over at our construction site! We were finished demolition in just under a month and since then progress on the excavation and preparation for shoring has been moving steadily. This next step is predicted to take about 6 months to complete, and it will involve digging deep enough for our 5-level …

3

Demolition is Finished

Things couldn’t be better at our site! In under a month we’ve completely removed the buildings that used to stand at the corner of Yonge and Grenville and are in the process of cleaning up the mess so we can get ready to build. We’re happy to see that work on our project is moving …